CIP FY 2023
Project Number: CB-2233
Funding Source: Water Utilities Capital
Location: Beginning at the lake and continuing north and then west paralleling FM 1148
Budget: $3,094,624
Type: Drought Response Pipeline Construction
Start Date: 05/12/2022
Completion Date: 08/02/2023
Details: The project includes the installation of approximately 15,000 linear feet of 12” diameter pipeline. This project will also provide for the installation of submerged piping and discharge manifold into Possum Kingdom Lake. The City holds a Texas Pollutant Discharge Elimination System permit with the Texas Commission on Environmental Quality, authorizing the discharge of reverse osmosis concentrate produced by the Possum Kingdom Raw Water Roughing Facility back into Possum Kingdom Lake.
Status: Construction
| | | | | | |
Programmed | Feasibility | Pre Design | Design | Bidding | Construction | Closeout |
Last Project Update: 8/18/23
Project Contacts:
- Katherine Beeman, Project Manager 325-725-3415
- Kent Hackworth, Project Inspector 325-725-3589