Possum Kingdom RO Concentrate Line Phase 2

CIP FY 2024

Project Number: CB-2365

Funding Source: Water Utilities Capital

Location: FM1148 between Highway 67 and Possum Kingdom Lake

Budget: $3,600,000.00

Type: Drought Response Pipeline Construction

Start Date: October 1, 2023

Completion Date: TBD

Details: This project includes the installation of about 15,000 linear feet of 12” diameter pipeline. The City holds a Texas Pollutant Discharge Elimination System permit with the TCEQ authorizing the discharge of reverse osmosis concentrate produced by the Possum Kingdom Raw Water Roughing Facility (PKRWRF) back into Possum Kingdom Lake.

Status: Bidding

       
ProgrammedFeasibilityPre DesignDesignBiddingConstructionCloseout

Last Project Update: 8/22/23

Project Contacts: 

  • Katherine Beeman, Project Manager 325-725-3415
  • Kent Hackworth, Project Inspector 325-725-3589