Northeast Water Treatment Plant SCADA Improvements

CIP FY 2023

Project Number: CB-2209

Funding Source: Water Utilities Capital

Location: 4210 East Lake Road

Budget: $776,584

Type: Water Treatment Plant Improvements

Start Date: 02/22/2022

Target Completion Date: 12/19/2022

Details: Upgrades and Improvements of the existing plant’s Supervisory Control and Data Acquisition (SCADA) system, including Programmable Logic Controllers, wireless communication, new control panels, and instrumentation and electronics.

Status: Closeout

       
ProgrammedFeasibilityPre DesignDesignBiddingConstructionCloseout

Last Project Update: 8/18/23

Project Contacts: 

  • Katherine Beeman, Project Manager 325-725-3415
  • Kent Hackworth, Project Inspector 325-725-3589