CIP FY 2023
Project Number: CB-2209
Funding Source: Water Utilities Capital
Location: 4210 East Lake Road
Budget: $776,584
Type: Water Treatment Plant Improvements
Start Date: 02/22/2022
Target Completion Date: 12/19/2022
Details: Upgrades and Improvements of the existing plant’s Supervisory Control and Data Acquisition (SCADA) system, including Programmable Logic Controllers, wireless communication, new control panels, and instrumentation and electronics.
Status: Closeout
| | | | | | |
Programmed | Feasibility | Pre Design | Design | Bidding | Construction | Closeout |
Last Project Update: 8/18/23
Project Contacts:
- Katherine Beeman, Project Manager 325-725-3415
- Kent Hackworth, Project Inspector 325-725-3589