CIP FY 2023
Project Number: not yet assigned
Funding Source: Water Utilities Capital
Location: Along East Highway 80 from Cottonwood Street to just pass Goliad Drive
Budget: $2,730,675 OPCC (Opinion of Probable Construction Cost)
Type: Waterline Improvement Construction
Start Date: Summer 2023
Projected Completion Date: Winter 2023
Details: This project is replacing 7,900 linear feet of 14” cast iron pipe with 14” PVC pipe, fire hydrants, valves, steel encasement, reconnection of existing water services, and asphalt and gravel pavement repair.
Status: Bidding
| | | | | | |
Programmed | Feasibility | Pre Design | Design | Bidding | Construction | Closeout |
Last Project Update: 8/18/23