Loop 322 24" Waterline from Maple Street Pump Station to Buffalo Gap Elevated Storage Tank

CIP FY 2024

Project Number: not yet assigned

Funding Source: Water Utilities Capital

Location: Run from Buffalo Gap Elevated Storage Tank to the Maple Street Pump Station south of Loop 322

Budget: Construction costs not determined

Type: Hydraulic and Capacity Improvement Construction

Start Date: Fall 2023

Completion Date: Spring 2025

Details: This project will increase pipeline capacity in a critical area of the distribution system to move large quantities of water east and west across the 2nd Pressure Plane. This is a continuation of the 2nd Pressure Plane Water Line Improvement along Rebecca Lane and Dub Wright Boulevard.

Status: Design

       
ProgrammedFeasibilityPre DesignDesignBiddingConstructionCloseout

Last Project Update: 8/18/23

Project Contacts: 

  • Katherine Beeman, Project Manager 325-725-3415
  • Kent Hackworth, Project Inspector 325-725-3589