CIP FY 2027
Project Number: Not yet assigned
Funding Source: Water Utilities Capital
Location: Off of Maple Street and Loop 322 near Kirby Lake
Budget: $4,140,000 OPCC (Opinion of Probable Construction Costs)
Type: Hydraulic and Capacity Construction
Start Date: Fall 2026
Completion Date: TBD
Details: This project increases the 2nd Pressure Plane pumping capacity of Maple Street Pump Station from X million gallons per day to 21 million gallons per day, with the addition of a 3rd pump and replacement of existing pumps. The project includes construction of a new 2 million gallon Ground Storage Tank.
Status: Programmed
| | | | | | |
Programmed | Feasibility | Pre Design | Design | Bidding | Construction | Closeout |
Last Project Update: 8/18/23
Project Contacts:
- Katherine Beeman, Project Manager 325-725-3415
- Kent Hackworth, Project Inspector 325-725-3589